The AREVA Wind M5000 is produced directly at Bremerhaven's quayside. In that way ideal preconditions for the transport to the offshore wind farms have been created. An in-house team of experienced technicians installs all components of the nacelle and the hub, including the sensitive components of the drive train. Thus AREVA Wind is capable to secure a persistent quality standard throughout the production process.
The AREVA Wind M5000 is concipated in such a way that for the installation at the offshore-site only the smallest possible number of installation steps is required. Besides the erection of the tower, just the same as it is with plants of previous generations, only nacelle and rotor have to be mounted. The converter system, transformer and switch gear are already installed on the tower 'ready-for-operation' in order to reduce the installation risk at the offshore location to a minimum.