December 2 2004 - Installation of the M5000 prototype completed |
Multibrid completes the installation of the first 5 MW-prototype with Multibrid Technology almost in record-breaking time.
|
read more |
|
December 22nd 2004 - First prototype of the M5000 offshore turbine connected to the grid |
Exactly 3 weeks after the erection of the Multibrid M5000 tower head, the first electricity was fed into the grid of Bremerhaven's utility.
|
read more |
|
November 29 2004 |
The middle tower section was installed late in the afternoon of the 25th. In the evening the nacelle and the hub were carried to their destination. On Friday the wind velocity was too high to continue with the erection. The second container was installed on the platform at the 27th followed by the top tower section.
|
read more |
|
November 25 2004 |
During the night from the 23rd to the 24th of November the tower sections were carried from the Kaiser Port to their destination. In best weather conditions the lowermost tower segment was lifted with a special purpose crane onto the adapter to the concrete tower and flanged to it.
|
read more |
|
November 23 2004 |
The steel sections of the tower were loaded on a barge in Bremen this morning. They will arrive this late afternoon in Bremerhaven and be carried on heavy load carriers to the construction site of the prototype.
|
read more |